Construction of a greenfield road, the Bulk Logistics Node and the Stanage Bay Road intersection (work package WP10002), described as the highest-value civil package on the ASMTI project. The remote site, 1.5 hours from Rockhampton, required drill-and-blast rock excavation, major culverts and steel-fibre concrete pavements, and the team worked through range fires and significant flooding.

Completed on the contracted date for practical completion with no liquidated damages applied.

multi-layer road pavement
15 km
culverts, up to 7-cell link slab
11
MRTS39 & MRTS40 concrete pavement
2,100 m³
imported fill
90,000 m³
pavement material
80,000 m³
rock excavation incl. blasting
10,000 m³

Scope of works

  • Clearing, grubbing and ground surface treatment along 15 km of alignment
  • 10,000 m³ of rock excavation including blasting at two locations
  • 90,000 m³ of imported Class A2 fill and 80,000 m³ of imported pavement material
  • 11 culverts, up to 7-cell 3.6 m x 3 m link slab culverts
  • 2,100 m³ of MRTS39 & MRTS40 concrete pavement
  • Shotcrete batter protection, drains and waterway barrier works
  • Service location, protection and relocation
  • 50-space car park for the Precinct B facility

Project gallery

  • Sealed pavement beside the prepared formation
  • New formation with erosion-control matting on the batters
  • Crew finishing a concrete slab beside the boom pump
  • Formwork for a culvert wingwall
  • Night pour of the steel-fibre concrete pavement
  • Geofabric laid ahead of the pavement material

The scope of the works were challenged by a number of major weather events along with impacts of the COVID 19 pandemic, however the Bellequip team continued to overcome these challenges and produced a compliant end product that met the project requirements.