Banana Shire Council · Cracow, QLD

Cracow Road Upgrade

Project overview

Section-by-section upgrade of Cracow Road between Taroom and Cracow to make the road more resilient to flooding and to improve sight lines, grade, width, signage and surfacing. Works included concrete floodway replacements, new box culverts and gravel and stabilised-gravel approaches, delivered under staged traffic on a live road in a remote location.

Completed within the date for practical completion, with no liquidated damages applied.

road sections upgraded
11
concrete floodways
8
excavation
10,808 m³
pavement
4,452 m³

Scope of works

  • Clearing and grubbing across 3.7 km of total alignment, including removal of 50 large trees
  • Removal of existing concrete slabs and culverts
  • 10,808 m³ of excavation, including 2,399 m³ of rock excavation
  • Subgrade treatment, 4,452 m³ of pavement and 14,238 m² of 2% GB stabilisation
  • Eight concrete floodways totalling about 260 m in length
  • RCBC and RCP culverts with end structures, plus 1,881 m³ of rock protection
  • Waterway barrier works with coffer dams and temporary diversions
  • 412 guide posts and new signage

Project gallery

  • Crew placing concrete for a floodway slab
  • Excavators working on the road formation
  • Stabiliser and water tanker on the pavement
  • Grader shaping a bend through the ranges
  • Spreader truck working the new pavement
  • Completed concrete floodway with rock protection

Council is satisfied with the quality and completion of the works delivered. No significant safety issues arose during construction, and all works were undertaken in accordance with relevant standards and site safety requirements.

Client reference — Banana Shire Council