Banana Shire Council · Cracow, QLD
Cracow Road Upgrade
Project overview
Section-by-section upgrade of Cracow Road between Taroom and Cracow to make the road more resilient to flooding and to improve sight lines, grade, width, signage and surfacing. Works included concrete floodway replacements, new box culverts and gravel and stabilised-gravel approaches, delivered under staged traffic on a live road in a remote location.
Completed within the date for practical completion, with no liquidated damages applied.
- road sections upgraded
- 11
- concrete floodways
- 8
- excavation
- 10,808 m³
- pavement
- 4,452 m³
Scope of works
- Clearing and grubbing across 3.7 km of total alignment, including removal of 50 large trees
- Removal of existing concrete slabs and culverts
- 10,808 m³ of excavation, including 2,399 m³ of rock excavation
- Subgrade treatment, 4,452 m³ of pavement and 14,238 m² of 2% GB stabilisation
- Eight concrete floodways totalling about 260 m in length
- RCBC and RCP culverts with end structures, plus 1,881 m³ of rock protection
- Waterway barrier works with coffer dams and temporary diversions
- 412 guide posts and new signage
Project gallery
Council is satisfied with the quality and completion of the works delivered. No significant safety issues arose during construction, and all works were undertaken in accordance with relevant standards and site safety requirements.