Project overview
An eroding tributary of Kroombit Creek near Thangool was cutting deeper with every flow. Bellequip stabilised it with rock chutes, reshaped the banks and revegetated the site, then stayed on to maintain and monitor it until the planting was established.
Completed ahead of the date for practical completion, with all project objectives exceeded.
- rock chute grade-control structures
- 2
- rock placed
- 3,081 m³
- tubestock specified
- 3,143
- ground cover at end of maintenance
- 80%+
Scope of works
- Clearing and grubbing of a 1.40 ha design footprint and a 260 m access track
- Two rock chutes (83 m and 57 m long, 7 m wide) with rock toe, filter layer, geofabric and cut-off walls
- 3,081 m³ of D50 450 mm rock plus keyed 1 m boulders
- Reprofiling of near-vertical banks to 1V:3H and backfilling of the existing channel
- Rootball logs pinned to 3 m hardwood piles to roughen the channel
- Flow-steering bunds, topsoiling and ameliorants
- Seeding, tubestock planting and temporary irrigation installation
- Biosecurity wash-down, as-constructed survey and RPEQ certification
- Post-construction maintenance, weed control and monitoring reporting